Internal Order

Once a year, network operators order the maximum firm exit capacity for the network interconnection point zones, calculated in accordance with the standardised process pursuant to § 13 of Cooperation Agreement VII, to process transports within the GASPOOL market area. This order takes place on 15 July each year for the following calendar year (base year).

ONTRAS is responsible for the submission of a complete internal order by downstream network operators pursuant to § 11 (4) within a period of ten working days by way of a statement of acceptance or rejection.

On submitting a statement of acceptance for the order, ONTRAS is obliged to reserve the resulting contractually agreed capacity to this downstream network at the network interconnection point zones. The internal ordering takes place online via the ONTRAS-Portal, which can be found under "Customer login" on the ONTRAS website. The conditions of use for the ONTRAS-Portal can be found in the download area under "ONTRAS Terms and Conditions".

If the ONTRAS Portal is not available, or a customer login is not possible, the internal order must be promptly submitted to ONTRAS using the "Internal Order" form.

Your Contact -
Erik Bauer
Netzvertragsmanagement
Phone
+49 341 27111-2923
Fax
+49 341 27111-2870
Sylvia Dathe +
Sylvia Dathe
Netzvertragsmanagement
Phone
+49 341 27111-5809
Fax
+49 341 27111-2870